After 2 weeks of delays due to snow and rain, it looks like two dry days beginning on Sunday 03/06 will allow the final foundation slabs to be poured on Monday 03/07. Here you see the removal of all slab insulation, removal of all water from the building,
installation of wire mesh on the upper slab areas, and installation of 3 columns for the 2nd floor beam.
installation of wire mesh on the upper slab areas, and installation of 3 columns for the 2nd floor beam.