Saturday, June 25, 2011

Infrastructure phase: status update

Sorry for the lack of new photos for the past three weeks. While we continue to make progress, little of it is visually interesting, and your blog photographers have been otherwise preoccupied. I hope to resume the photo stream shortly.

Status Update:

Interior: Plumbing and HVAC infrastructure are now installed. Electrical work begins next week.

Exterior: Skylights are now installed. Windows are due in momentarily. For hardscaping, concrete footings have been poured. Retaining and architectural walls are next, but we are currently re-evaluating wall heights/configurations.